Initiative Tail

The two stages between "every plan item is done" and delivery, and the driver that replans an initiative which can no longer advance.

Project Lifecycle owns the graph and the rollup that opens this tail; Plan Review owns everything before dispatch.

Scope

The Build Loop is authoritative on assembly. This page owns the evaluation stage, the stalled-initiative replan and its generation cap, and degraded-boot parking.

INTEGRATING is what the loop does today, and the rest of this page describes it as built and enforced. The build loop retires it: assembly stops being a stage, a unit merges onto the trunk as it finishes, the trunk is green at all times, and the software boots at the end of every slice. What this stage exists to catch, a set of individually-verified parts that nobody ever ran together, is answered continuously by the trunk gates instead of once at the end. Until the trunk gates exist, INTEGRATING is the only thing catching it, so the state diagram and ## INTEGRATE below remain the contract rather than a superseded one.

EVALUATING survives unchanged. Scoring the delivered whole against the charter's criteria is a judgement no gate makes, and it stays fail-closed.

The problem

The general loop ran plan, execute, and verify, then stopped. Every plan item passing its own review gate completed the plan, the project, and the objective.

That is a real assurance about each piece and none at all about the whole. An initiative could deliver a set of individually-verified parts that nobody had ever assembled, run together, or checked against what the objective actually asked for, and the board would show it as delivered. Three smaller leaks kept that from even being reliable per piece:

  • a WORK plan item could declare zero expected artifacts, which disarmed the fail-loud zero-artifact guard, so a chat-only run with no output reached review as though it had produced something;
  • the lifecycle-only baseline execution service walked any task straight to COMPLETED, gate or no gate;
  • the coordination parent rollup derived subtask status from run outcomes, which report success before verification.

Shape

stateDiagram-v2
    EXECUTING --> INTEGRATING: every item done
    INTEGRATING --> EVALUATING: assembly job passed its review gate
    EVALUATING --> COMPLETED: every success criterion met
    INTEGRATING --> EXECUTING: an item regressed
    EVALUATING --> EXECUTING: an item regressed
    INTEGRATING --> SUPERSEDED: replan
    EVALUATING --> SUPERSEDED: replan
    INTEGRATING --> FAILED: assembly will not assemble
    EVALUATING --> FAILED: the judgement cannot run

EXECUTING -> COMPLETED does not exist. Neither does the project's ACTIVE -> COMPLETED. Delivery has exactly one predecessor in both machines, so the tail cannot be skipped by construction rather than by whichever service happens to be wired. The back-edges carry a regression: an item that stops being done (integration findings routed back as rework) reopens the build without a replan.

Both tail stages reach FAILED. A replan resolves the tail failures somebody chooses to re-plan; without the direct edge, the ones nobody re-plans sit in the tail with no reachable exit, which is the deadlock shape that made a whole project undeletable. See Every state has an exit a writer can always take.

INTEGRATE

engine/initiative/integrate.py mints one ordinary task and dispatches it through the normal work pipeline.

This stage is the root assembly, and on a plan that recursed it is no longer the only one. An item with children is the assembly of the work below it, dispatched as an ordinary plan item with an assembly brief over its own children and its own namespaced evidence paths, keyed on its whole address in the tree (.synthorg/integration/<slug>/<slug>/, one segment per level) so no two containers can write over each other, so a wide fan-in at the top becomes the narrow ones the recursion-depth sweep measured. Those carry their container's plan_item_id like any other item, so item_is_done reads them normally and derive_plan_status opens INTEGRATING only once every subtree has assembled. The root's brief then names the plan's workstreams rather than every leaf in the tree: listing a hundred titles is what a flat render becomes the moment a plan is a tree. engine/assembly.py owns the brief, the paths, and the stakes ladder that both callers share. See recursive-decomposition.md.

Making it an ordinary task is the whole design. It inherits the entire existing verification chain with no second oracle written for it: the review gate runs run_completion_gates, so the build/test oracle reads its CodeExecutionRecord rows and refuses an unverified or failing build, the completion-oracle peer review fails closed without a distinct reviewer, and output policy, red team, and vision all apply. A bespoke "integration checker" would have been a second, weaker gate.

Three shape decisions carry weight:

decision why
forced LEAF (WorkItem.leaf_required) splitting an assembly job hands the pieces back to separate agents, which is the state the stage exists to end
plan_id set, plan_item_id unset it belongs to the initiative without implementing any plan item, so every derivation over items ignores it and it cannot distort the rollup that opened the stage. That provenance rule still identifies exactly the ROOT assembly: a subtree assembly carries its container's plan_item_id and is that item's progress
id derived from the plan id (uuid5) idempotency with no "already started" flag to drift from reality: a re-fired stage finds the existing row and stops

It declares two expected artifacts, .synthorg/integration/report.md (what was assembled, where the runnable deliverable is, what had to be fixed) and .synthorg/integration/end-to-end.txt (the run's own output, verbatim). They are workspace-relative paths rather than prose because the declared-artifact check can only probe a path (see agent-execution.md), and a stage whose declarations no probe can reach arms nothing: a chat-only integration would reach review with the check silently abstaining. The stage cannot know where a given objective's deliverable lives, so it does not guess at that path; it names two files of its own that the brief instructs the agent to write, and checks those. The zero-tool-call proxy still applies, and the assembly is judged by the same review chain as any other task. It runs one stakes level above the plan's highest item, because assembly is the first point the whole thing runs and the last point before delivery. Its acceptance criteria are the objective's own.

Outcome, read from the task's persisted status on the next rollup recompute:

  • COMPLETED (so the gate passed it): plan INTEGRATING -> EVALUATING;
  • FAILED / REJECTED / CANCELLED: the replan trigger fires with INTEGRATION_FAILED;
  • anything else: still working, nothing happens.

EVALUATE

engine/initiative/evaluate.py runs a bounded session in which the accountable lead judges the delivered whole against the objective's success criteria. It is modelled on the SHIP retrospective session: detached, wall-clock bounded, turn and cost capped, never raising into the rollup.

The verdict is per-criterion and evidenced (EvaluationReport), not a single thumbs-up. Two invariants make it load-bearing:

  • every criterion is judged exactly once. A submission that drops one, or invents one the objective does not have, is rejected back into the session for correction rather than accepted with the unanswered criteria treated as met;
  • PARTIAL is not a pass. An initiative is delivered when the objective is met, not mostly met.

The session's tools are read-only by design (workspace read and list). A session that could change what it is judging could turn its own failing verdict into a passing one. They are scoped to the plan's own project workspace (engine/workspace/paths.py::project_workspace_dir), not the shared agent-workspaces base root, so listing a directory returns the deliverable rather than a tree of sibling projects and the paths in the material resolve as written.

What the judge is given

The material (engine/initiative/evaluate_brief.py) carries the objective and its criteria, the plan items and their declared artifacts, and the recorded test-run evidence for the project: the CodeExecutionRecord rows written from the commands that actually ran. The list is newest-first and bounded. "The test suite passes" is then judged against what ran rather than against a claim, and the brief no longer directs the session to run things it has no tool to run.

The verdict is a record

The verdict decides whether an initiative delivered, so it is persisted before anything acts on it. initiative_evaluation_report is an append-only, dual-backend table keyed unique on (plan_id, attempt), carrying the summary and every CriterionVerdict with its outcome and evidence (persistence/evaluation_report_protocol.py, composing AppendOnlyRepository). A re-evaluation is a new attempt with its own row rather than an edit of the old one: overwriting would erase the evidence the replan points at.

evaluate.py::_record writes it before the status write, so a lost CAS race on the completion transition costs the transition rather than a judgement that cost real money and cannot be re-derived. A record write that fails parks the plan: it returns False and _run never reaches _apply. A verdict nobody can read afterwards is, to every later reader, no verdict, and no verdict parks rather than completes; completing on one would leave an initiative marked delivered with nothing to point at when asked why. The next recompute re-judges within the attempt cap, so the cost is a re-judgement rather than a delivery with no evidence behind it.

GET /plans/{plan_id}/evaluation returns the attempts newest-first, and the dashboard's PlanEvaluationPanel renders each criterion with the judge's evidence, so a parked initiative explains itself instead of leaving the operator with unmet_count=2 in a log line and nothing else. Empty attempts is the honest answer for a plan nothing has judged; the plan's own status distinguishes that from one parked at EVALUATING because no verdict landed.

Fail closed

No report, an unresolvable lead, no provider, a timeout, an objective with no criteria: every one of those leaves the plan sitting at EVALUATING with a warning on each recompute. Nothing completes an initiative on a missing verdict.

This is the deliberate inverse of the red-team gate's policy, and it is the point of the whole change: an evaluation that did not happen is not a pass. An operator resolves a parked plan by replanning or cancelling.

Auto-replan

replan_initiative was fully built and reachable only from a human POST /plans/{id}/replan. Nothing noticed when an initiative ran out of ways to advance, so a stalled plan simply hung until someone looked. engine/initiative/replan_trigger.py is that missing driver. The successor lands in PENDING_REVIEW, which is the human gate the product already has: the organisation gets itself unstuck, the operator still decides.

What counts as stalled

A shape, not a duration: the plan has outstanding work and none of it can move without a new decision. There is no threshold to tune and no timer, and the derivation is exact the moment the last live item dies.

Several cases are deliberately excluded, each because replanning would destroy something:

not a stall why
work still moving (CREATED through IN_REVIEW) it is simply in flight
a human wait (AWAITING_INPUT, AUTH_REQUIRED) the org is waiting on the operator; a replan would discard the question rather than answer it
a WORK item whose task row does not exist yet dispatch writes the plan's EXECUTING status before it creates the task rows, so treating this as dead would replan every initiative during its own dispatch window
an undecided DECISION item that carries options a human wait like the row above: somebody can still answer it, and the parked question is how they are asked
a BLOCKED task parked on a reason someone will still end (oracle_escalated, reviewer_unstaffed, red_team_unstaffed, no_capable_agent) the same shape of wait as the two rows above, expressed through BLOCKED instead of its own status. BLOCKED is otherwise dead by default, so this one reads the REASON rather than the status (ATTENDED_BLOCKED_REASONS): without it, asking a human to decide a review is itself what makes the initiative look stalled, and the replan supersedes the plan the question was about

The two tail stages produce verdicts no derivation over items can see (every item is COMPLETED when integration fails), so INTEGRATION_FAILED and EVALUATION_UNMET are carried in by the stage and re-confirmed by the plan still sitting in the stage that produced them.

A DECISION item has no task row by construction, so the missing-row carve-out above is narrowed to WORK items, which is the only case its justification (the dispatch window) describes. Read the other way it made every undecided decision count as live for ever: a plan whose one outstanding item was a decision could never derive a stall, so the replan trigger never fired and the initiative hung with nothing watching. An undecided DECISION with no options counts as dead: nobody can resolve it, so the plan derives BLOCKED and replans. plan_validation.validate_decision_options additionally rejects an optionless DECISION at parse time, so the unanswerable shape stops being producible.

Loop safety

Plan.replan_generation counts how many times an initiative has replanned itself. A successor opened automatically carries its predecessor's generation plus one; a human replan resets it to zero, because a human decision is not a runaway. Past engine.auto_replan_max_generations the trigger refuses.

Every fire re-reads the plan and re-confirms the stall before doing anything, which is what makes a redelivered rollup event harmless: the first replan supersedes the plan, and every later attempt reads a superseded plan and stops.

A refusal is an answer

The trigger owns two refusals nobody else can see: the generation cap and the engine.auto_replan_enabled master switch. Both used to be evaluated inside the detached task, where the rollup could not learn of either, so it read "a trigger is attached" as "a replan will happen" and asked again on every recompute. A live run scheduled a replan that was refused three times in twelve minutes and kept going, while its plan read executing with four of seven items dead and a warning rewritten in the log as the only trace.

So the rollup asks, and the trigger answers with a ReplanDisposition. SCHEDULED, ALREADY_RUNNING and UNAVAILABLE all mean something is or will be happening; DISABLED and BUDGET_EXHAUSTED mean no automatic route remains, and so does no trigger being attached at all. Those three are one outcome with three reasons.

No automatic route left

An initiative in that state needs a person, and the loop's own rule for reaching one is by exception: a question needing an answer. So engine/initiative/stall_escalation.py keeps exactly one OPEN initiative:stalled decision per plan, sends one notification on the edge that opens it, and leaves the plan where it is, still open to a manual replan while the operator thinks. Later passes find the decision open and say nothing: neither a second alert, nor a second ask of the replan trigger, since an initiative waiting on a person is not one to keep considering for an automatic replan, and refusing it at WARNING every cadence would be the repeating log line the decision replaced.

One OPEN rather than one ever. Answering the decision closes it, and a plan that is still stalled on the next pass raises a fresh one. That is the correct reading: the answer was taken, it did not move the initiative, and the operator is owed the news rather than silence. What must hold for it to stay bounded is that answering CHANGES something, which is why the answer is re-confirmed against the live state on the branch the recorded reason selects rather than re-derived over the items alone.

Failing the plan there was the tempting answer and is the wrong one twice over. It is the system deciding whether an initiative the operator may still want should end, which is a de-escalation of a decision the human owns; and it does not even fix the surface it looks like it fixes, because the objective task is held at IN_PROGRESS until the plan COMPLETES, so the initiative's own board row would not move either. What moves instead is the plan's own surface: the open decision is resolved beside the plan row (api/_plan_decisions.py) and rendered as "Awaiting your decision", so executing stops being the whole story.

Both answers act. Approving replans the initiative once on the operator's authority through ReplanTriggerService.grant, which applies neither the cap nor the switch (both bound what the org does unasked, and somebody has just asked) and stamps generation zero on the successor. Rejecting fails the plan with the stall reason. A plan that recovered in between is re-confirmed and left alone either way.

Degraded boots

Each collaborator degrades independently, and none of them degrades into a completion:

unwired behaviour
integrate stage (no work pipeline) plan parks at INTEGRATING, WARNING per recompute
evaluate stage (no provider) plan parks at EVALUATING, WARNING per recompute
replan trigger (no coordinator) a derived stall escalates to the operator as a decision, exactly as an exhausted budget does
stall escalation (no approval store) a derived stall fails the plan with its reason; parking it silently is what left a dead initiative reading EXECUTING
extension escalation (no approval store) a workstream needing another extension is not held at EXECUTING; the plan advances with the gap unaddressed, surfaced later at the judged EVALUATING gate rather than by a second parking mechanism
retro capture (no memory layer) finished work does not feed a retrospective back

Parking is the honest outcome while something can still move it: an initiative whose pieces were never assembled has not delivered, and an initiative nobody scored has not been shown to meet its objective. The operator's remedy is one the product already has: replan (legal from both tail stages) or cancel.

Parking a plan nothing can move is a different thing, and it is a deadlock. A derived stall that no automatic route can clear has no remaining actor of its own: the items are all dead, the stages cannot fire, and no later event changes either fact. The remaining actor is a person, so it escalates; only where nothing in the deployment can ask one does the rollup fail the plan with the stall reason rather than parking it. An unsuccessful coordinate(...) fails the plan exactly as a raised one does. Both were the same collapse in a live run: five tasks died in 1.85s and the plan sat at EXECUTING for ever, because only a raise had been treated as failure.

Independently means one subsystem each, six of them, all separate from the rollup. The rollup activates once persistence and the task engine exist, which is before setup has configured a provider, so a first boot legitimately produces a rollup with no tail; each initiative_* spec waits on what that one collaborator actually needs and activates on a later reconciler pass, attaching onto the already-wired rollup without re-registering the observer, so each comes online with no restart.

Declaring the six as one subsystem would make the union of their requirements a precondition for any of them, and the table above would be a lie: a boot with no coordinator would get no integrate stage either. The stall escalation is its own subsystem for the sharper version of that reason: it is needed exactly when the replan trigger is absent or refusing, so folding it into the trigger's spec would leave a boot with one reading as covered for the other. Extension escalation is separate again, on the same reasoning: it raises a different decision under a different idempotency key (see Workstream Extension), and a plan whose stall escalation is wired but whose extension escalation is not should still read that gap rather than borrow the sibling's liveness. Their liveness is read one probe per collaborator for the same reason: a shared probe let a tail whose retro capture never resolved (memory blocked because no embedder was chosen) read as converged, and the reconciler never revisits that.

The retro capture additionally declares a teardown and rebuild_on_change, because it holds both memory backends for the life of the instance and those are replaceable while the process runs; without them it would keep writing into layers nothing else reads.

The evaluate stage therefore reads the replan trigger per verdict rather than capturing one at construction. The two converge on their own schedules, so a coordinator arriving after the provider registry would otherwise leave the stage holding the None it was built with and park every unmet initiative for the life of the process.

There is exactly one wiring path per collaborator. Re-running the rollup's own wiring attaches nothing: a post-setup rewire list is the drift subsystem reconciliation exists to reject, and it is what left the tail declining on every deployment while the capability read as live.

Settings

Every key below is read when the tail fires, so an edit applies to the next run of it rather than needing a restart.

key default purpose
engine.auto_replan_enabled true master switch for the stall trigger
engine.auto_replan_max_generations 2 generation cap stopping a runaway chain
engine.auto_replan_timeout_seconds 600 ceiling on one re-decomposition
engine.integration_stage_timeout_seconds 1800 ceiling on minting + dispatching the assembly job
engine.evaluation_session_max_turns 10 evaluate session turn cap
engine.evaluation_session_cost_ceiling 1.0 evaluate session spend ceiling
engine.evaluation_session_timeout_seconds 300 evaluate wall-clock ceiling
coordination.jit_extension_planning_enabled false master switch for the extension mechanism; see Workstream Extension
engine.auto_extension_enabled true automatic-authority switch for granting an extension unasked, once the master switch is on
engine.auto_extension_max_generations 2 generation cap, per workstream, stopping a runaway extension chain

What proves the tail ran

Reading the code cannot settle whether the tail fires, and neither can watching a run go by: three live runs each ended with someone asserting from inspection that the machinery was wired, while no plan had ever reached INTEGRATING. So the claims are stated here as rows a query returns, and a run that cannot produce those rows has not proved anything regardless of what its log said.

The oracle blocked an unverified build. The blocking authority is the integration task's ordinary review gate, whose build/test oracle is a pure function of persisted code_execution_record rows.

evidence where it is read back
the integration task exists, plan_id set and plan_item_id null, and is not completed tasks row, GET /tasks/{id}
no passing test evidence backs it code_execution_record rows for the project
the plan did not advance out of integrating GET /plans/{id}, GET /plans/{id}/transitions
the stall was named, not swallowed plans.replan_generation, the initiative.integration.failed event
the stall reached a person once it could go no further the initiative:stalled row in GET /approvals, PlanRow.pending_decision
no evaluation report was written GET /plans/{id}/evaluation is empty

A passing wave marked the objective complete.

evidence where it is read back
a report with one verdict per objective criterion, each met, each with evidence GET /plans/{id}/evaluation
the report was written before the status changed initiative_evaluation_report.created_at against the lifecycle_transitions row
the evaluating -> completed hop names initiative-evaluate GET /plans/{id}/transitions
the project mirrored and the objective task closed projects, tasks
the deliverable exists and runs .synthorg/integration/ in the project workspace

The transition ledger carries the actor for every hop, so "who moved this" is a query rather than an inference. That is load-bearing for the second table: a completed plan whose transition names anything but initiative-evaluate reached the status by a path this design forbids, and the row is the only place that shows it.

The end-to-end run walks a run through the dashboard and reads each row back.

Enforcement

scripts/check_verified_completion_paths.py (pre-push + CI) holds up the three structures this page depends on: the forbidden edges stay forbidden and COMPLETED keeps exactly one predecessor in both machines; only the evaluate stage writes PlanStatus.COMPLETED; and both plan-shaped models still enforce that a WORK unit declares a deliverable. Opt out per-line with # lint-allow: verified-completion -- <reason>.